| 
Electrical
Power Expansion Project Major U.S. Baker Increasing It's Capacity Electrical
Power Expansion Project Emerson Process Management dispatched an Electrical
Power Engineer to the facility to review the existing single line drawings and
to bring them up-to-date. This confirmed the client's concern that additional
power would be required to support the new production lines. During the plant
visit the engineer suggested a conceptual design that would resolve the problem.
The design incorporated a new 480V substation. It also included a new, double
- ended switchgear lines - up in an outdoor powerhouse, to be served by two, 2500
KVA transformers supplied by the local utility company. Each 3000A bus was
designed to be served by a 3000A main breaker and separated by a 3000A tie breaker.
In the case of transformer failure the design provided for the plant to be served
from the remaining source by opening the associated main breaker and closing the
tie. Emerson Process Management was awarded the project to provide a complete
engineering package for contractor installation, including bid packages, and to
coordinate all activity with the local utility. Utility Capacity &
Expansion Study Emerson Process Management dispatched a lead mechanical
engineer to make a complete study of the existing mechanical utility systems,
including electrical power, steam, plant and instrument air, and process water.
Emerson Process Management analyzed capacity utilization for every piece
of equipment in each of the utility systems. This included chillers, boilers,
compressors, transformers and the like. Once this analysis was complete
Emerson Process Management provided the client with a report that outlined which
equipment had excess capacity and which equipment did not. Recommendations were
also made regarding expanding the utilities to match the production expansion
needs. Back to Success Stories |